The $13 Billion Supercarrier That Launches Jets With Magnets: Inside USS Gerald R. Ford

Military Explained Staff Military Explained Staff

The USS Gerald R. Ford cost about $13 billion, the most the U.S. Navy had ever spent on a single warship when it was delivered. It is also the first American carrier to throw jets into the air with electromagnets instead of steam, and its latest deployment lasted 326 days, the longest for a U.S. carrier since the Vietnam War.

The short version of how it got there: the ship showed up years late, was handed over without working bomb elevators, and then spent most of two long deployments in the middle of real crises.

Aircraft carrier USS Gerald R. Ford with its small island and wide flight deck leaving Newport News, Virginia, with a tugboat alongside
The Ford leaves Newport News Shipbuilding under its own power for the first time, April 8, 2017. Photo: U.S. Navy / Mass Communication Specialist 2nd Class Ridge Leoni, public domain, via Wikimedia Commons.

What $13 billion buys

The Navy's budget estimate for building the ship was $12,964.0 million, according to a Feb. 1, 2019, Congressional Research Service report. In 2006, Congress had capped the cost at $10.5 billion, plus adjustments for inflation and other factors. By 2018 the cap had been raised to $13.0 billion, and the program still needed an extra $1.39 billion in cost-to-complete funding.

CommissionedJuly 22, 2017
Length1,106 feet (337 m)
DisplacementAbout 100,000 tons, fully loaded
ReactorsTwo A1B nuclear reactors
Top speedOver 30 knots (35 mph)
Aircraft75 or more
CrewAbout 2,600 ship's company; 4,539 with air wing and staff
CostAbout $13.0 billion to build

Magnets instead of steam

For more than 50 years, Navy carriers have launched jets with steam catapults. The Ford's Electromagnetic Aircraft Launch System, or EMALS, swaps the steam piston for a linear induction motor. The pitch was a smoother ride for the aircraft and a faster tempo: the Navy set a requirement of 160 sorties a day for 30 days, a 33 percent improvement over a Nimitz-class carrier, with a four-day surge of 270.

Then came the test numbers. From November 2019 to September 2020, testers logged 3,975 launches and recoveries. EMALS averaged 181 launches between failures serious enough to scrub a mission. The requirement was 4,166. The new arresting gear that catches landing jets managed just 48 recoveries between failures. Bloomberg News reported the Pentagon's findings in January 2021.

F/A-18E Super Hornet lifting off a test runway in a cloud of dust during an electromagnetic catapult trial, red-and-white tower behind
An F/A-18E Super Hornet launches during an EMALS test at Lakehurst, N.J., Dec. 16, 2010. This is the test site, not the Ford. Photo: U.S. Navy, public domain, via Wikimedia Commons.

The Navy cleared EMALS for every type of naval aircraft in February 2020, and the ship has kept flying. On its 2023-24 deployment the strike group flew 10,396 sorties.

Fewer sailors, three times the electricity

The Ford was designed around electricity. The Navy told the Senate in 2015 that its propulsion plant has three times the electrical generating capacity of a Nimitz-class carrier's, power that EMALS and a new radar need.

The other promise was people. The Navy planned to cut 663 jobs from the ship's crew, nearly 1,200 counting the air wing, and to save $4 billion per ship over 50 years. Military Times reported in 2014 that the ship's company would be about 2,600 sailors, roughly 600 fewer than on a Nimitz-class carrier. The old 180-person berthing areas gave way to rooms of about 40 racks.

Those are design goals, not measured savings.

Late, over budget and missing its bomb elevators

Steel was first cut in 2005. The carrier floated out of its dry dock on Oct. 11, 2013, with the ship's sponsor, Susan Ford Bales, starting the flooding. Delivery had been planned for 2015. The Navy took the ship on May 31, 2017.

Woman in a white hard hat and safety glasses presses buttons on a control panel as photographers and a camera operator crowd behind her
Ship's sponsor Susan Ford Bales begins flooding Dry Dock 12 at Newport News, Va., Oct. 11, 2013. Photo: U.S. Navy / Chris Oxley, public domain, via Wikimedia Commons.

It arrived without a key piece. Bloomberg reported in November 2018 that the Navy's costliest warship was delivered without the 11 magnetic elevators that lift bombs from the magazines to the flight deck. Four times since 2015, the elevators had made unsafe, uncommanded movements. Navy Secretary Richard Spencer called the elevator "our Achilles heel."

To prove the hull could take a beating, the Navy set off three powerful underwater explosions near it in 2021. The last came on Aug. 8.

Huge column of gray water and spray erupting beside the flight deck of USS Gerald R. Ford during a shock trial at sea
The Ford rides out the final explosion of its full ship shock trial, Aug. 8, 2021. Photo: U.S. Navy / Mass Communication Specialist 3rd Class Novalee Manzella, public domain, via Wikimedia Commons.

Two deployments, one record

The Ford's first full deployment began in May 2023. After Hamas attacked Israel on Oct. 7, the strike group moved to the Mediterranean, and the trip was stretched by 76 days. It returned to Norfolk on Jan. 17, 2024, after 239 days away: 10,396 sorties, 17,826 flight hours and 83,476 nautical miles, about 96,000 miles, or nearly four trips around the Earth.

The second deployment left Norfolk on June 24, 2025. In October the Ford was rerouted to the Caribbean for the largest U.S. naval buildup there in generations, and it took part in the January operation that captured Venezuelan President Nicolás Maduro. It then joined the opening days of the Iran war from the Mediterranean and moved into the Red Sea in early March, according to the Associated Press.

Sailor in a green jersey signals beside an E-2D Hawkeye radar plane on the Ford's flight deck with open ocean behind
A sailor signals to tension the catapult before an E-2D Hawkeye launches from the Ford in the Caribbean Sea, Jan. 31, 2026. Photo: U.S. Navy / Petty Officer 2nd Class Alexander Casco, public domain, via Wikimedia Commons.

On March 12, 2026, a fire broke out in the main laundry. It took about 30 hours to put out. The Navy said it was not combat related. Reports differ on how many sailors lost their bunks, from about 100 to more than 600. The Ford pulled into Souda Bay, Crete, on March 23 for repairs.

It reached Norfolk on May 16, 2026, after 326 days at sea. By the AP's count, only USS Midway in 1973 (332 days) and USS Coral Sea in 1965 (329 days) stayed out longer. USS Nimitz was away 341 days in 2020-21, but that total included weeks of COVID-19 isolation ashore.

So is the Ford a triumph or a money pit? The record supports both. The magnets, the elevators and the new reactors blew up the schedule and the bill. But once the ship was at sea, it went where it was sent: the Caribbean, the Mediterranean, the Red Sea.

The next test is wear. The AP noted concerns about the strain a 326-day cruise puts on the crew and the ship. And the Navy chose in 2017 to keep EMALS and the arresting gear on the first three Ford-class carriers, so whatever the Ford learns will follow its sisters.